Project Updates
---------------------
This page records factual updates shared by buyers and publicly available sources.
Updates are for information and record-keeping purposes only.
5 January 2026
• Site visit conducted by buyers
• CRM team reiterated possession timeline of 8–10 months
• Buyers reiterated request for delay compensation as per Agreement for Sale
31 December 2025
• RERA completion date missed as per original declaration
• Consent letter circulated by promoter seeking extension up to 31 Mar 2027.